ANALISIS PENGARUH PERUBAHAN BEBAN TERHADAP KONSUMSI BATUBARA, HEAT RATE DAN EFISIENSI TERMAL PLTU INDOEKA UNIT 1
DOI:
https://doi.org/10.30872/electrops.v3i2.16576Keywords:
Steam Power Plant, Fuel Consumption, Heat Rate, Thermal EfficiencyAbstract
With the availability of energy needs every year, the government on the other hand must also reduce exhaust emissions to reduce the greenhouse effect. One way to reduce exhaust emissions is by energy efficiency. Because steam power plants use burning coal to heat air into dry steam, fuel consumption, heat rate and thermal efficiency will influence changes in the load of steam power plants. Before researchers carry out calculations to find SFC values, plant heat rate and thermal efficiency, researchers must select data from the database. The selection of this data refers to the lowest generation load and the following data increases the load by 10 MW from the previous data, until the maximum load is obtained in multiples of 10 MW. Obtained load values of 40 MW, 50 MW, 60 MW, 70 MW, 80 MW and 90 MW from data selection. As the electricity loading value increases, the Net SFC value tends to get lower. This shows that under high electricity loading conditions, the amount of coal consumed per kWh is less than under low electricity loading conditions. As the electrical loading value increases, the NPHR value will become lower. This shows that at high loads, the noise from a generating unit will also be higher. On the other hand, at low loads, the noise from a generating unit will also decrease. As the electrical loading value increases, the thermal efficiency value of the Indoeka Unit 1 Steam Power Plant also increases and can be said to be efficient. This shows that under high load conditions, the percentage between the energy produced and the energy consumed is also higher.References
Rahmad, Riki, “Geomorfologi Kalimantan Seri Geomorfologi Indonesia”, 3rd ed, Bukittinggi: STKIP Ahlussunnah Bukittinggi, 2015.
Pemerintah Provinsi Kalimantan Timur, “Rancangan Akhir Rencana Pembangunan Jangka Menengah Daerah (RPJMD) Provinsi Kalimantan Timur Tahun 2018-2023,” Pemerintah Provinsi Kalimantan Timur. Kalimantan Timur, 2018.
Kementrian Koordinator Bidang Perekonomian RI, “Siaran Pers HM.46/432/SET.M.EKON.3/11/2021 Upaya Penurunan Gas Rumah Kaca Melalui Langkah Strategis pada Sektor Kritikal Perubahan Iklim.” Republik Indonesia. Jakarta, 2021.
Presiden republik Indonesia, “Undang-undang Republik Indonesia Nomor 16 Tahun 2016 Tentang Pengesahan Persetujuan Paris Atas Konvensi Kerangka Kerja Persarikatan Bangsa-bangsa Mengenai Perubahan Iklim”, Jakarta: Presiden Republik Indonesia, 2016.
Markori dan Idris, Zainuddin, “Analisis Produksi Energi Listrik Pada Pembangkit Listrik Tenaga Uap Batubara Dengan Matlab,” Jurnal Teliska, vol.5, no. 2, pp. 61–67, Mei 2013.
PT PLN (Persero), “Laporan Tahunan 2015 Annual Report 35 MW Untuk Indonesia,” PT PLN (Pesero), Jakarta Selatan, 2015.
Ghurri, Ainul, “Konsep Managemen Energi,”. Denpasar: Jurusan Teknik Mesin-Universitas Udayana, 2016.
Yudistira I.R, Nerry, “Analisis Konsumsi Batubara pada PLTU Tanjung Awar-awar Unit 1 dengan Menggunakan Metode Least Square,”. Surabaya: Institut Teknologi Sepuluh November, 2015.
Buku Panduan Operator DCS Pt. Indonesia Energi Dinamika Independent Power Produser, PT Indonesia Energi Dinamika, Tenggarong Seberang, Indonesia, 2020.
Syahputra, Ramadoni, “Pembangkit Tenaga Listrik”, Yogyakarta: Universitas Muhammadiyah Yogyakarta, 2020.
Standar Operasi Pusat Listrik Tenaga Gas, SPLN 80 : 1989, 30 Agustus 1988.
Downloads
Additional Files
Published
Issue
Section
License
The copyright of this article is transferred to ELECTROPS : Jurnal Ilmiah Teknik Elektro and when the article is accepted for publication. the authors transfer all and all rights into and to paper including but not limited to all copyrights in the ELECTROPS : Jurnal Ilmiah Teknik Elektro. The author represents and warrants that the original is the original and that he/she is the author of this paper unless the material is clearly identified as the original source, with notification of the permission of the copyright owner if necessary. The author states that he has the authority and authority to make and carry out this task.
The author states that:
- This paper has not been published in the same form elsewhere.
- This will not be submitted elsewhere for publication prior to acceptance/rejection by this Journal.
A Copyright permission is obtained for material published elsewhere and who require permission for this reproduction. Furthermore, I / We hereby transfer the unlimited publication rights of the above paper to ELECTROPS : Jurnal Ilmiah Teknik Elektro. Copyright transfer includes exclusive rights to reproduce and distribute articles, including reprints, translations, photographic reproductions, microforms, electronic forms (offline, online), or other similar reproductions.
The author's mark is appropriate for and accepts responsibility for releasing this material on behalf of any and all coauthor. This Agreement shall be signed by at least one author who has obtained the consent of the co-author (s) if applicable. After the submission of this agreement is signed by the author concerned, the amendment of the author or in the order of the author listed shall not be accepted.
Rights / Terms and Conditions Saved
- The author keeps all proprietary rights in every process, procedure, or article creation described in Work.
- The author may reproduce or permit others to reproduce the work or derivative works for the author's personal use or for the use of the company, provided that the source and the Informatika Mulawarman copyright notice are indicated, the copy is not used in any way implying the ELECTROPS : Jurnal Ilmiah Teknik Elektro approval of the product or service from any company, and the copy itself is not offered for sale.
- Although authors are permitted to reuse all or part of the Works in other works, this does not include granting third-party requests to reprint, republish, or other types of reuse.